|
home -> blogs -> PMP Certify! |
PMP Certify! |
|
Disclaimer: The information provided here are purely my opinion, based on my learning and I do not represent any of the organizations. The information provided is to share my success path to others and might contain errors or not latest. Always check yourself for latest details directly from their websites. |
PMI’sms
Initiation -> Planning -> Execution -> Controlling -> Closing Total
1 21 7 8 2 39
Core Processes: These have clear dependencies and have to be essentially performed in the same order.
Facilitating Processes: These are not optional and are performed intermittently and as needed during project planning.
Power and Politics:
Power: Potential ability to influence behavior, to change the course of events, to overcome resistance, and to get people to do things that they would not otherwise do.
Politics: Is about getting collective action from a group of people who may have different interests
Programs – Group of related Projects – tendency to continue
Portfolio – Group of unrelated Projects
Framework:
Project Coordinator
|
|
V
Project Expeditor
Cost: Original Plan
PV Today (EV) BAC
|-------------------------------------|---------------------------|
AC | ETC EAC
|-------------------------------------|---------------------------------------------|
|
Scope |
||
|
Charter -> Scope Statement -> WBS |
||
|
Work Packages/WBS Dictionary |
||
|
Product Analysis: Value Engineering, Quality Function Deployment |
||
|
Accuracy of Estimates: |
|
|
|
Order of Magnitude |
Done during Initiating |
- 25% to +75% |
|
Budget Estimate |
Done during Planning |
-10% to +25% |
|
Definitive Estimate |
Done during Planning |
- 5% to +10% |
|
Project Planning Methodology |
A structured approach used to guide the project team during development of the project plan |
Use Hard tools (Project Management Software) and Soft tools (facilitated meetings) |
|
CWBS |
Contractual WBS |
For Seller |
|
OBS |
Organization Breakdown Structure |
Work components to Organization Units |
|
RBS |
Resource Breakdown Structure |
|
|
BOM |
Bill of Material |
Manufacturing |
|
PBS |
Project Breakdown Structure |
Same as WBS; used when WBS is used instead of BOM |
|
Cost/Schedule |
|||
|
Project Network Diagram – also called PERT (Program Evaluation & Review Technique) |
PDM – Precedence Diagraming Method aka AON – Activity on Node |
4 relations: Finish to Start (Common) Finish to Finish Start to Start Start to Finish (Rare) |
|
|
PERT & CPM can be drawn only using ADM/AOA |
ADM or Acitivity Diagraming Method Aka AOA – Activity on Arrow |
Use Dummies Only one relation: Finish to Start |
|
|
Hammock |
When two activities meet |
Portions of Network also called Fragnet/Subnet |
|
|
GERT – Graphical Evaluation Review Technique |
Loops & Conditional Branches |
Probabilistic Treatment |
|
|
PERT – drawan using AOA |
Uses weighted average; is rarely used |
For time or cost |
|
|
CPM – drawn using AOA |
Uses most likely estimate |
Can have dummies |
|
|
Duration Compression |
Crashing – Putting more resource Increases cost |
Fast-Tracking – Doing in Parallel instead of Sequence Rework and more risky |
|
|
Monte-Carlo Analysis |
Simulation for What-if Conditions |
Does not use PERT formula; uses path convergence |
|
|
Analogous Estimating |
Topdown approach |
Is a kind of Expert Judgement |
|
|
Reserve |
Contingency, Buffer |
10% in general |
|
|
Float/Slack = LS – ES or LF – EF; also called Free Slack, Total Slack & Path Slack |
Amount of time a task can be delayed without delaying the successor |
Critical Path tasks will have zero slack |
|
|
Total Slack |
Amount of time a task can be delayed without delaying the project |
||
|
Project Slack |
Amount of time a project can be delayed without delaying the externally imposed date |
||
|
Lag |
Waiting time between tasks |
Concrete Curing Time |
|
|
Lead |
Successor task can start early |
|
|
|
Network Diagram – For Dependency |
Bar/Gantt Chart – Progress Reporting |
Milestone – Status Reporting for Management |
|
|
CV = EV – AC |
+ ve Is good |
- ve is bad (over budget) |
|
|
SV = EV – PV |
+ is good |
- ve is bad (behind schedule) |
|
|
CPI = EV/AC |
CPI > 1 is good |
CPI < 1 is bad |
|
|
SPI = EV/PV |
SPI > 1 is good |
CPI < 1 is bad |
|
|
EAC = BAC/CPI |
Estimate At Completion |
|
|
|
ETC = EAC - AC |
Estimate to Complete |
|
|
|
VAC = BAC - EAC |
Variance At Completion |
|
|
|
PV = FV/ (1+r) n |
Present Value |
Today’s value for future value |
|
|
NPV |
Net Present Value |
Years included so go with $ amount (higher the better) |
|
|
IRR |
Internal Rate of Return |
Higher the % the better |
|
|
BCR |
Benefit to Cost Ratio |
Payback to Cost; > 1 is good |
|
|
Payback Period |
Time when you start getting returns |
Lower the better |
|
|
Opportunity Cost |
NPV2 – NPV1 |
Return on choosing one over another |
|
|
Sunk Costs |
Expended Costs |
SCORE Project 20 m |
|
|
PERT = (P + 4ML + O)/6 |
Std. Dev = (P-O)/6 |
Variance = [P-O/6]2 |
|
|
+- 6 Sigma = 99.99 |
|
|
|
+- 3 Sigma = 99.73 |
||
|
+- 2 Sigma = 95.46 |
||
|
+- 1 Sigma = 68.26 |
||
|
Direct Cost |
Project cost |
Salary, Travel, Awards, Material |
|
Indirect Cost |
For group and for all projects; % of direct cost |
Tax, Fringe Benefits, Janitorial Service |
|
Fixed Cost |
Does not change with work |
Rental, setup |
|
Variable Cost |
Changes with work |
Material, Wages |
|
Crashing Cost |
Find the difference between Crash Cost and Original Cost |
The lowest is the choice |
|
|
||
|
Heuristics |
Rule of Thumb |
80/20 |
|
Quality |
|
|
Design of Experiments |
Tire/Wheel in a car |
|
Benchmarking |
Comparing with others |
|
Ishikawa Diagram |
Cause and Effect or Fishbone Diagram |
|
Flow Chart |
How elements flow through |
|
Quality Audit |
Part of QA – To check overall process |
|
Inspection (review, walkthrough, audit) |
Part of QC – To check specific deliverable |
|
Control Chart |
Upper and lower control limit; Specification limits; Baseline or mean; Rule of seven; Assignable cause; Out of control |
|
Paretto Diagram |
A Histogram – 80/20: 80% of problems are caused by 20% of causes |
|
KAIZEN |
Continuous Improvement |
|
Variable – Characteristic like Shape, Wieght |
Attribute – Measurement like inches, pounds |
|
|
|
|
HR |
|||||
|
RAM - Responsibility Assignment Matrix |
War Room |
||||
|
Resource Histogram |
Resource Gantt Chart |
|
|||
|
Fringe Benefits |
Insurance, Bonus etc. |
||||
|
Perks |
Corner office, Executive Dining |
||||
|
Conflict Management |
|||||
|
Smoothing |
Both agree or similarities and do not talk about differences |
also called Accommodating |
|||
|
Forcing |
Its my way |
also called Competing, Assertive |
|||
|
Withdrawal |
I give up |
also called Avoidance |
|||
|
Compromising |
Both give up little |
|
|||
|
Confronting |
Solve the problem |
Also called Problem Solving or Collaborative |
|||
|
Maslow’s Theory |
Pyramid |
Self Actualization Esteem Social Safety Physiological |
|||
|
McGregor’s Theory |
Theory of X & Y |
X – Need to be watched Y – Independent |
|||
|
Herzberg’s Theory |
Hygiene Factors |
Motivating Agents |
|||
|
Halo Effect |
Engr -> PM |
|
|||
|
Expectancy Theory |
Awards <-> Work |
Achievement Theory |
Importance of friendship and sense of camarederie in work environment |
||
|
Source of Conflict |
|
||||
|
|
|||||
|
|
|||||
|
Communication |
|||
|
Formal Written |
Complex Problems, Charter/Plan, Distance |
Informal Written |
Memo, Email, Notes |
|
Formal Verbal |
Prezo, Speech |
Informal Verbal |
Meetings |
|
|
|
|
|
|
Channels of Communication |
N*(N-1)/2 |
|
|
|
Risk |
||
|
Acceptance |
Active – Contingency Plan & Fallback Plan |
Passive – Take it easy |
|
Avoidance |
Avoid the root cause or trigger |
|
|
Transference |
Deflection |
Insurance |
|
Mitigation |
|
|
|
Sensitivity Analysis |
Done in Quantitative Analysis |
To determine which risks have the most potential impact on the project |
|
Risk Reports to communicate to stakeholders |
Issues Logs, Action-item Lists, Jeopardy Warnings & Escalation Notices |
|
|
Data Precision Ranking |
How well understood is the risk? What data we have for ris? |
|
|
Assumption Analysis/Testing |
|
|
|
Procurement |
||
|
Fixed Price Contract |
Risk: More for Seller |
|
|
Cost-reimbursable Contract |
Risk: More for Buyer |
|
|
Time & Material Contract |
Combo – Fixed Rate & Long period |
|
|
IFB |
Invitation for Bid |
|
|
RFP |
Request for Proposal |
|
|
RFQ |
Request for Quote |
|
|
IFN |
Invitation for Negotiation |
|
|
CIR |
Contractor Initial Response |
|
|
Independent Estimate |
Most concerned for Cost |
|
|
Difference between Contract Closeout and Administrative Closure |
Admin Closure: Lessons Learnt |
Contract Closeout: At the end of contract; this occurs first and before AC. Procurement Audit Need more documentation |
|
Privity |
A -> B -> C |
A has no control on C |