home -> blogs -> PMP Certify!

PMP Certify!  
 

Disclaimer: The information provided here are purely my opinion, based on my learning and I do not represent any of the organizations. The information provided is to share my success path to others and might contain errors or not latest. Always check yourself for latest details directly from their websites.

 

PMI’sms

 

Initiation -> Planning -> Execution -> Controlling -> Closing                                 Total

      1                   21                 7                      8                      2                                    39

 

Core Processes: These have clear dependencies and have to be essentially performed in the same order.

 

Facilitating Processes: These are not optional and are performed intermittently and as needed during project planning.

 

Power and Politics:

 

Power: Potential ability to influence behavior, to change the course of events, to overcome resistance, and to get people to do things that they would not otherwise do.

 

Politics: Is about getting collective action from a group of people who may have different interests

 

Programs – Group of related Projects – tendency to continue

Portfolio – Group of unrelated Projects

 

Framework:

 

Project Coordinator

|

|

V

Project Expeditor

 

Cost:  Original Plan

 

                        PV           Today (EV)             BAC

|-------------------------------------|---------------------------|

                        AC                     |                     ETC                            EAC

|-------------------------------------|---------------------------------------------|

 

           

Scope

Charter -> Scope Statement -> WBS

Work Packages/WBS Dictionary

Product Analysis: Value Engineering, Quality Function Deployment

Accuracy of Estimates:

 

 

Order of Magnitude

Done during Initiating

- 25% to +75%

Budget Estimate

Done during Planning

-10% to +25%

Definitive Estimate

Done during Planning

- 5% to +10%

Project Planning Methodology

A structured approach used to guide the project team during development of the project plan

Use Hard tools (Project Management Software) and Soft tools (facilitated meetings)

CWBS

Contractual WBS

For Seller

OBS

Organization Breakdown Structure

Work components to Organization Units

RBS

Resource Breakdown Structure

 

BOM

Bill of Material

Manufacturing

PBS

Project Breakdown Structure

Same as WBS; used when WBS is used instead of BOM

 

Cost/Schedule

Project Network Diagram – also called PERT (Program Evaluation & Review Technique)

PDM – Precedence Diagraming Method aka AON – Activity on Node

4 relations:

Finish to Start (Common)

Finish to Finish

Start to Start

Start to Finish (Rare)

PERT & CPM can be drawn only using ADM/AOA

ADM or Acitivity Diagraming Method

Aka AOA – Activity on Arrow

 Use Dummies

Only one relation: Finish to Start

Hammock

When two activities meet

Portions of Network also called Fragnet/Subnet

GERT – Graphical Evaluation Review Technique

Loops & Conditional Branches

Probabilistic Treatment

PERT – drawan using AOA

Uses weighted average; is rarely used

For time or cost

CPM – drawn using AOA

Uses most likely estimate

Can have dummies

Duration Compression

Crashing – Putting more resource

Increases cost

Fast-Tracking – Doing in Parallel instead of Sequence

Rework and more risky

Monte-Carlo Analysis

Simulation for What-if Conditions

Does not use PERT formula; uses path convergence

Analogous Estimating

Topdown approach

Is a kind of Expert Judgement

Reserve

Contingency, Buffer

10% in general

Float/Slack = LS – ES or LF – EF;

also called Free Slack, Total Slack & Path Slack

Amount of time a task can be delayed without delaying the successor

Critical Path tasks will have zero slack

Total Slack

Amount of time a task can be delayed without delaying the project

Project Slack

Amount of time a project can be delayed without delaying the externally imposed date

Lag

Waiting time between tasks

Concrete Curing Time

Lead

Successor task can start early

 

Network Diagram – For Dependency

Bar/Gantt Chart – Progress Reporting

Milestone – Status Reporting for Management

CV = EV – AC

+ ve Is good

- ve is bad (over budget)

SV = EV – PV

+ is good

- ve is bad (behind schedule)

CPI = EV/AC

CPI > 1 is good

CPI < 1 is bad

SPI = EV/PV

SPI > 1 is good

CPI < 1 is bad

EAC = BAC/CPI

Estimate At Completion

 

ETC = EAC - AC

Estimate to Complete

 

VAC = BAC - EAC

Variance At Completion

 

PV = FV/ (1+r) n

Present Value

Today’s value for future value

NPV

Net Present Value

Years included so go with $ amount (higher the better)

IRR

Internal Rate of Return

Higher the % the better

BCR

Benefit to Cost Ratio

Payback to Cost; > 1 is good

Payback Period

Time when you start getting returns

Lower the better

Opportunity Cost

NPV2 – NPV1

Return on choosing one over another

Sunk Costs

Expended Costs

SCORE Project 20 m

PERT = (P + 4ML + O)/6

Std. Dev = (P-O)/6

Variance = [P-O/6]2

       

 

 

+- 6 Sigma = 99.99

+- 3 Sigma = 99.73

+- 2 Sigma = 95.46

+- 1 Sigma = 68.26

Direct Cost

Project cost

Salary, Travel, Awards, Material

Indirect Cost

For group and for all projects; % of direct cost

Tax, Fringe Benefits, Janitorial Service

Fixed Cost

Does not change with work

Rental, setup

Variable Cost

Changes with work

Material, Wages

Crashing Cost

Find the difference between Crash Cost and Original Cost

The lowest is the choice

Heuristics

Rule of Thumb

80/20

 

Quality

Design of Experiments

Tire/Wheel in a car

Benchmarking

Comparing with others

Ishikawa Diagram

Cause and Effect or Fishbone Diagram

Flow Chart

How elements flow through

Quality Audit

Part of QA – To check overall process

Inspection (review, walkthrough, audit)

Part of QC – To check specific deliverable

Control Chart

Upper and lower control limit;

Specification limits;

Baseline or mean;

Rule of seven;

Assignable cause;

Out of control

Paretto Diagram

A Histogram – 80/20: 80% of problems are caused by 20% of causes

KAIZEN

Continuous Improvement

Variable – Characteristic like Shape, Wieght

Attribute – Measurement like inches, pounds

 

 

 

HR

RAM - Responsibility Assignment Matrix

War Room

Resource Histogram

Resource Gantt Chart

 

Fringe Benefits

Insurance, Bonus etc.

Perks

Corner office, Executive Dining

Conflict Management

Smoothing

Both agree or similarities and do not talk about differences

also called Accommodating

Forcing

Its my way

also called Competing, Assertive  

Withdrawal

I give up

also called Avoidance

Compromising

Both give up little

 

Confronting

Solve the problem

Also called Problem Solving or Collaborative

Maslow’s Theory

Pyramid

Self Actualization

Esteem

Social

Safety

Physiological

McGregor’s Theory

Theory of X & Y

X – Need to be watched

Y – Independent

Herzberg’s Theory

Hygiene Factors

Motivating Agents

Halo Effect

Engr -> PM

 

Expectancy Theory

Awards <-> Work

Achievement Theory

Importance of friendship and sense of camarederie in work environment

Source of Conflict

  1. Schedules
  2. Priorities
  3. Resources
  4. Technical Opinions
  5. Administrative Procedures
  6. Cost
  7. Personality

           

 

 

Communication

Formal Written

Complex Problems, Charter/Plan, Distance

Informal Written

Memo, Email, Notes

Formal Verbal

Prezo, Speech

Informal Verbal

Meetings

 

 

 

Channels of Communication

N*(N-1)/2

 

 

Risk

Acceptance

Active – Contingency Plan & Fallback Plan

Passive – Take it easy

Avoidance

Avoid the root cause or trigger

 

Transference

Deflection

Insurance

Mitigation

 

 

Sensitivity Analysis

Done in Quantitative Analysis

To determine which risks have the most potential impact on the project

Risk Reports to communicate to stakeholders

Issues Logs, Action-item Lists, Jeopardy Warnings & Escalation Notices

Data Precision Ranking

How well understood is the risk?

What data we have for ris?

Assumption Analysis/Testing

 

 

 

Procurement

Fixed Price Contract

Risk: More for Seller

 

Cost-reimbursable Contract

Risk: More for Buyer

 

Time & Material Contract

Combo – Fixed Rate & Long period

 

IFB

Invitation for Bid

 

RFP

Request for Proposal

 

RFQ

Request for Quote

 

IFN

Invitation for Negotiation

 

CIR

Contractor Initial Response

 

Independent Estimate

Most concerned for Cost

 

Difference between Contract Closeout and Administrative Closure

Admin Closure:
Can occur at the end of each phase and at the end of project

Lessons Learnt

Contract Closeout: At the end of contract; this occurs first and before AC.

Procurement Audit

Need more documentation

Privity

A -> B -> C

A has no control on C